TRAFFIC MANAGEMENT PLANS & ETON NOTICES

EToN (Electronic Transfer Of Noticing). Our in house Symology certified team are able to upload, manage and close down EToN notices for your telecommunications projects whether it be decommissioning/maintenance or a new install. Providing you with frequent status updates, you will remain completely informed at every stage whilst our team manage the detail on your behalf.

 

Other ServicesContact Us

Traffic Management Plans

Using the latest in traffic management design software, cone 10 and BricsCAD, we can produce outstanding, professional traffic and event management plans which are clear and informative.

Our staff are trained on the software by the software experts, CONE.

We have supplied traffic management plans for major contracts from utility and telecommunications to major events such as the London Marathon and Prudential Ride London, ask for examples, we’d be glad to show you some of our work.

EToN Permits

Electronic Transfer of Notifications, Symology. Our team are fully trained and experienced on ETON and we manage notices for our clients from start to finish.

Please be aware that when applying for EToN Permits, there are a strict set of guidelines and procedures which we have to follow, and as a result, the mandatory notice period which we need from you is different depending on the length of the works that you have planned. We cannot guarantee that your permit will be granted if you do not provide us with the required notice period, so please check below to ensure that your application will fall within our minimum notice requirements.

EToN Permits - Minimum notice

Works with durations between 0-3 days5 days notice
Works with durations between 4-10 days12 days notice
Works with durations exceeding 11 days4 calendar months notice
Works requiring road closures and / or temporary traffic orders4 calendar months notice

To view the technical specification for the electronic transfer of notifications